Return to Intellectual Capital

 

Successful Implementation of

Business Initiatives

     Very few business initiatives of any complexity are 100% certain to achieve the objectives set at the price and on the schedule planned. For IT projects in particular, there is a substantial body of research that shows that 65% to 70% with budgets of over $1M fail, in the sense of running significantly over budget or schedule, or failing to deliver a substantial portion of the promised benefits. About half of the failures are total failures, where the project gets cancelled or delivers no value; the other half implements something but over budget, over schedule and missing some expected benefits.

     The second most common reason for IT project failures is lack of adequate organizational change management (a CEO once made an astute observation about why his initiatives had a high success rate: "early on, I conduct public executions of a few prominent non-supporters, and promote a few supporters; afterwards the company takes the initiative much more seriously"). The most common reason for failure, of course, is poor project or program management.

     Companies with a lot of failed and failing projects, should determine:

  1. which projects are in trouble and should be shut down, and which are worth trying to rescue;

  2. which projects appeared to be going along OK but in fact are risky, and what the quantified risk is; and

  3. what the true costs and benefits of proposed projects are, after adjusting for risk factors.

     Risk-adjusted pricing and benefits is a methodology Kawaru developed (originally for a large technology company) to allow managers to determine the true cost and potential benefits of a project. Managers evaluate which success factors are in place at the particular point in time during a project when they conduct an evaluation then adjust costs and benefits to reflect the resulting risk score.

     There is a quick diagnostic version that a manager can do in a few minutes, which is based on the premise:

        risk comes in two major dimensions:

  1. Probability (how likely the adverse event is)

  2. Magnitude (what impact the adverse event will have).

     For example, building a new high rise in San Francisco, the likelihood of cost overruns due to planning department and board of supervisors interference is high, but the magnitude is low to low-medium. The likelihood of a major earthquake during a vulnerable stage of construction is very low, but the magnitude is very high.

 

 

     Applied to an IT project, this involves the manager going through a checklist of the major risk factors (program management; resistance to change; executive sponsorship; size and duration of project; etc.) and scoring each as low, medium, or high on both dimensions. The manager would then aggregate the scores (using some judgment; this is not a purely quantitative process) into a single 3 X 3 matrix. If the low/low box were checked for the project, that means there is at least a 90% chance that the project would deliver most of the projected benefits close to on time and budget. If high/high, stop wasting your money. If you view the lower left box as "low/low," then, in most situations, checks in the three boxes to the lower left mean 'go,' in the three on the upper right mean 'stop;' and the diagonal from the upper left to lower right means 'find ways to mitigate risk before proceeding.

    This proves more useful when a manager completes two matrices: one for project cost/schedule; and one for project benefits. With enough data points, a company might find that for it a check in the middle box of the benefits matrix means there is a 60% risk factor to the benefits (the project would, statistically speaking, deliver only 40% of the projected benefits). This means that the cost per dollar of benefits is really 2.5 times as much as the notional original analysis indicated. If a project is expected to cost $5M and deliver $25M in benefits, or 5:1, but the middle box was checked, then risk adjusted benefits are really only $10M, or 2:1. If a company invests an additional $1M getting the risk factor down to 40%, then risk adjusted benefits increased to $15M, or 2.5:1 overall and 5.0.1 incrementally ― a good investment. Apply similar logic on the project cost/schedule side: calculate the risk in the schedule and budget estimates, then adjust cost/schedule to reflect the risks, and recalculate the cost/benefit ratio.

     While specific cost/schedule and benefit risk percentages vary company to company, the methodology can be used in a more qualitative way to achieve similar result. Basically, if an evaluation of the current situation puts the project in the middle square of the matrix for cost/schedule, and the company can lower it to one of the bottom left three boxes for another $xx,xxx, then clearly that would be a good thing to do. If a company can also reduce the risk on the benefits side for a fairly small $$$ investment, that would be even better. Doing both would be excellent. However, continuing to evaluate project decisions as if there is no risk to either project cost and schedule or to project benefits from the decision could be disastrous.

 

 

Return to Intellectual Capital

Send questions or comments about this web site to: tingram@kawaru.com
Copyright © 2000 Kawaru Research

Feedback  Legal Notice